St. Louis Cardinals- Busch Stadium

Location

700 Clark Ave, St. Louis, MO 63102, USA

Project Size

1,100,000 sq ft

Completed Date

2020

Prime Contractor

Thomas Industrial Coatings, Inc.

Client

St. Louis Cardinals

Value

Private

About Project

TIC completed a five-year project with the St. Louis Cardinals to access, complete surface preparation, and recoat all steel structures in Busch Stadium. The scope of work was broken into 11 different phases arranged by areas of the ballpark.

Work efforts were completed in the off-season and coordinated around the team’s schedule during the season. Special events, such as concerts and other sporting events, also came into play when coordinating a schedule. TIC completely mobilized out of the stadium while it was in use for events.

There were multiple means of access used to reach the different structures comprising the stadium, including man lifts, scissor lifts, mobile and stationary scaffolding and spider baskets.

Aerial View

— Related Projects —