LRWRA- Adams Field WRF Clarifier Repairs

Location

11 Clearwater Dr, Little Rock, AR 72204, USA

Project Size

14,000 sq ft

Completed Date

2022

Prime Contractor

Thomas Industrial Coatings, Inc.

Client

Little Rock Water Reclamation Authority

Value

$405,000

About Project

TIC traveled to Little Rock, Arkansas in the spring of 2022 to complete repairs on a clarifier at Adams Field Reclamation Facility.

The scope of work included grout injection between the clarifier trough and SSPC SP-7 brush blasting three clarifier troughs. The coating application included an epoxy resurfacing and a ceramic epoxy topcoat with a finished dry film thickness of 100 mils.

Bug holes in the concrete were filled with an epoxy filler. A saw cut was made to terminate the liner in the trough areas.

Aerial View

Drone View

— Related Projects —